AES Andres / El Dia
Two major national grid power generators are out for maintenance works. The coal-fired 356 MW Punta Catalina 1 is off the grid for 45 days as of 29 March 2022. And now the Andres AES gas-fired power plant for six days starting on 7 May 2022. This is the explanation for the power outages that are affecting the country as of late.
Read more in Spanish:Diario LibreEl DiaDiario Libre
11 May 2022