And that's just the abutments. Then they have to set or cast-in-place beams, then a roadbed deck and then guard rails and striping. I'm thinking May - weather depending
I'd bet the beams are made and ready to go.
 

MOC1

Newbie
Oct 22, 2002
42
10
8
Estrella is a large international engineering firm. I think they know what they're doing. But as we al know the DR can have it's own quirks.
 
  • Like
Reactions: JD Jones

chico bill

Silver
May 6, 2016
13,217
6,998
113
You've been away from civilization too long, my friend. -:LOL:
As an engineer who has built several similar structures, I can tell you good crews (even the ones I had on projects from Korea, Turkey and Thailand would have had this bridge built long ago
 
  • Like
Reactions: Auryn

windeguy

Platinum
Jul 10, 2004
42,991
6,420
113
As an engineer who has built several similar structures, I can tell you good crews (even the ones I had on projects from Korea, Turkey and Thailand would have had this bridge built long ago
They did have the extensive delay in buying the additional land.
 

monfongo

Bronze
Feb 10, 2005
1,226
156
63
The didn't acquire the property to widen it until a few mos. ago, that's where the screwed up.
 

JD Jones

Moderator:North Coast,Santo Domingo,SW Coast,Covid
Jan 7, 2016
13,480
9,708
113
  • Like
Reactions: cavok

chico bill

Silver
May 6, 2016
13,217
6,998
113
Hey CB, take a look. They were pouring last night!


Once that starts to set they can start backfilling in the outsides while it's curing.
They can strip after a week, that's a full week's work, backfill is another 3-4 weeks work, in the meantime they can also pour the other side, set the pads for beams and bring them in after a month of cure (if the beams are already pre-cast and cured or if they are fabricated steel) then they can start to form a deck, place steel pour and cure the deck (renderings show a concrete deck) then set or pour guard rails,
After that they backfill, compact and pour followed by asphalt on each side for new approaches, stripe the deck, replace the water supply pipe to Cangrejo and set new electric light poles....hmm I say April for the actual first black SUV with flashing lights to drive across. It will not be December 2023.
They also will need to have rock (boulders like we saw in Sosua) erosion protection to prevent future undermining of abutments
Remember nothing much gets done between mid-December and Three Kings
 

Tom0910

Well-known member
Sep 28, 2015
937
691
113
There are new photos of the heavy equipment arriving for the placement of the spans or whatever they are called and the pads are stripped of the forms or whatever they are called. It was on Facecrack posted by the El Lider page if anyone wants to look at or post the photos,that is above my pay grade.
 

rogerjac

Bronze
Feb 9, 2012
1,425
509
113
405921704_373441618679602_3770266118139553234_n.jpg
 

chico bill

Silver
May 6, 2016
13,217
6,998
113
I hope that's Cor-Ten steel and not needing sandblasting and painting in place.
Lots of welding to be done.
Won't be open this year that's a given
 
  • Like
Reactions: bachata

bachata

Aprendiz de todo profesional de nada
Aug 18, 2007
5,435
1,310
113
I hope that's Cor-Ten steel and not needing sandblasting and painting in place.
Lots of welding to be done.
Won't be open this year that's a given
Hopefully in my next trip Will be 100% complete ✅