3 weeksWhat's the "over/under" for the time to fix the bridge?
3 weeksWhat's the "over/under" for the time to fix the bridge?
You mean wait as in a year or so while the other bridge is rebuilt? Perhaps it can be repaired, but only time will tell.I guess you could use any of those "bridges". Haven't been on that road for some time now and what I remember the road is "doable" but it's not really worth it unless you have a "sturdy" vehicle. And guessing that everyone that really HAS to get over that river, it will most likely be heavily congested. So unless you cannot wait to cross I wouldn't bother.
More likely it called for a bolted or riveted plate joint design. Not even in DR would they have specified an unbutressed butt weld on a column. This bridge is a typical truss superstructure type. Probably need some very large cranes on both side to make repairsStructural steel doesn't break like that in a clean straight line. That was a butt joint that somebody welded together during the fabrication of the bridge parts. I guarantee you that wasn't in the fabrication drawings. It should have been one solid length of beam. The original fab shop cut corners to save money.
It can be repaired and 'fairly' soon. If it were me I would fly a engineering/bridge team in from the Southern US - These type of bridges are over every river from Louisiana to Oklahoma.You mean wait as in a year or so while the other bridge is rebuilt? Perhaps it can be repaired, but only time will tell.
We go to Puerto Plata every couple of weeks. It will be inconvenient.
May be a dumb question, but are they allowing people to walk across the bridge (in this case you could get a Moto up to it and then another Moto after you get across)? Or must you swim across the river? I think there are eels in that river though...Anybody else hear that the 'detour bridge' has collapsed from the heavy traffic ?
This will really re-route the Pto Plata/POP traffic........Santiago/Moca?
More likely it called for a bolted or riveted plate joint design. Not even in DR would they have specified an unbutressed butt weld on a column. This bridge is a typical truss superstructure type. Probably need some very large cranes on both side to make repairs
But is it surprising this bridge suffered a structural failure ?
With all the overloaded trucks, especially the past 2 years hauling boulders for the Marriot beach breakwater in Sousa, and never slowing down the vibration and wheel impact along with rust finally took its tool
Wonder when the last competent engineering inspection was done
I don't care who you are, that's funny.I've done a lot of steel construction over the years, both fab shop and in the field. This is a typical truss bridge and they would never have designed in a butt joint at that location even with bolted plates. Somebody screwed up in the fabrication shop and tried to hide it. And then somebody got paid to ignore it. But they will probably patch it up with welded plates and put extra paint on it to make it really strong.
How about two cranes? One either side tethered together making a triangle?I've done a lot of steel construction over the years, both fab shop and in the field. This is a typical truss bridge and they would never have designed in a butt joint at that location even with bolted plates. Somebody screwed up in the fabrication shop and tried to hide it. And then somebody got paid to ignore it. But they will probably patch it up with welded plates and put extra paint on it to make it really strong.
It's going to be difficult to lift with a crane though and get it back in place. I wouldn't be surprised if they jacked it up from below.
It should get inspected now though. If they find other butt joints like this they may have to scrap it.
People are taking guaguas to either side and walking across to take another guagua.May be a dumb question, but are they allowing people to walk across the bridge (in this case you could get a Moto up to it and then another Moto after you get across)? Or must you swim across the river? I think there are eels in that river though...
Tough to jack it up off the water.I've done a lot of steel construction over the years, both fab shop and in the field. This is a typical truss bridge and they would never have designed in a butt joint at that location even with bolted plates. Somebody screwed up in the fabrication shop and tried to hide it. And then somebody got paid to ignore it. But they will probably patch it up with welded plates and put extra paint on it to make it really strong.
It's going to be difficult to lift with a crane though and get it back in place. I wouldn't be surprised if they jacked it up from below.
It should get inspected now though. If they find other butt joints like this they may have to scrap it.
As you have experience of steel works and mine is in aircraft structure, why would you weld the fillet piece instead of bolt/rivet assembly? Welds have the possibility of failure to incorrect technique, weld penetration and corrosion.Tough to jack it up off the water.
They might be able to drag a deep beam over the place where the bridge deck dropped due to the seperated column and pull it up.
Then as you say butt weld the column and reinforce it with plates fillet welded each side?
Then hire an engineering firm to redesign a new bridge
Rivets and or bolts also rust and fail, maybe even faster than proper welds.As you have experience of steel works and mine is in aircraft structure, why would you weld the fillet piece instead of bolt/rivet assembly? Welds have the possibility of failure to incorrect technique, weld penetration and corrosion.
Just asking your opinion and comparing my industry to yours. Airplanes bend and flex just like bridges. No welded joints on airplane structures.
Well - a solution to "the trucks never slowing down, the vibration and wheel impact" could be remedied (or at least partially remedied )But is it surprising this bridge suffered a structural failure ?
With all the overloaded trucks, especially the past 2 years hauling boulders for the Marriot beach breakwater in Sousa, and never slowing down the vibration and wheel impact along with rust finally took its tool
Wonder when the last competent engineering inspection was done
But if a vehicle launces itself over a speed bum to fast and loses control even slightly and impacts the superstructure it's even worse tan going too fastWell - a solution to "the trucks never slowing down, the vibration and wheel impact" could be remedied (or at least partially remedied )
with the installation of substantial and well-signed speed bumps, once the repair or replacement is completed.
Doesn't solve the problematic mix of "Complexity, A Correct Job and Dominicans" though.